Notice
Protest
Determination
Dispute
Hearing

1. Executive Summary

Decision Requested

Issue written protest determination denying Skanska LTR 377 (March 13, 2026) supplemental protest on bridge deck thickness at Bridge No. 405/70N-W (northbound I-405 to westbound SR 522).

  • Recommendation: Deny — contract framework is strong regardless of discrepancy magnitude
  • Cost Exposure: $378,613 ROM claimed; below $1.5M DSC threshold; WSDOT exposure = $0
  • Risk Level: Low-to-moderate — contract language is clear; Skanska’s strongest argument is equitable (pre-bid coring impracticality on active I-405)

Core Question

Does Skanska’s reliance on as-built deck thickness drawings entitle it to a Differing Site Condition claim, or does TR 2.13.1’s explicit disclaimer and field verification requirement — combined with the Reference Document provisions (GP 1-01.3, GP 1-02.2) — place dimensional risk on the Design-Builder?

Penhall (demolition subcontractor) discovered deck thickness exceeding as-built documentation on Bridge 405/70N-W during active demolition on January 24, 2026. As-built drawings (Appendix N02_5) show 6.5–7” original deck plus ~1.5” 1996 overlay (total ~8–8.5”). Field measurements show 8.5” at the south end (effectively no discrepancy) to 10–10.5” at the north end (up to ~2.5” discrepancy). Skanska’s claim uses 7.0” as the as-built baseline, ignoring the documented 1996 overlay.

WSDOT issued a written determination on February 12, 2026 (SL 9727-264) denying the DSC on three grounds: (1) TR 2.13.1 explicitly disclaims dimensional accuracy of bridge as-builts and requires the Design-Builder to field verify existing dimensions; (2) as-built drawings (Appendix N2) are designated “R” (Reference Documents) in Appendix A1, which the DB relies on “at its own risk” per GP 1-01.3 and GP 1-02.2; (3) Form A/ITP 3.3.4 certification that Skanska inspected and examined the site. Skanska filed Notice of Protest 016 on February 26, 2026 (LTR 359) and a 55-page supplemental protest package on March 13, 2026 (LTR 377).

LTR 377 adds a Type (b) DSC argument (“physical conditions of an unusual nature”), rebuts all three WSDOT grounds, includes the Modjeski and Masters structural verification memo (which found no modification to demolition plans is needed despite increased dead load), and provides Penhall’s deck thickness mapping using an inflated 7.0” baseline. The protest response is pending.

Issue ID
DSC 008 / SKA-0308
Amount Claimed
$378,613 ROM
Schedule Claimed
34 calendar days
Status
Deny

2. Skanska Assertions and WSDOT Position

A TR 2.13.1 does not apply to demolition — only to design and fit-up Strong

Skanska Assertion (LTR 377)

TR 2.13.1 applies only to “design and fit-up of new construction interfacing with existing elements,” not to “verifying the internal composition of structures being entirely removed.”

WSDOT Position

TR 2.13.1 says “field measure and verify existing dimensions as required for their Work.” It does not carve out demolition from “their Work.” The word “dimensions” is not qualified. The contract does not distinguish between dimensions needed for new construction and dimensions needed for demolition planning. Knowing the deck thickness of a structure being entirely removed is plainly “required for their Work.” Demolition planning requires knowing what you are removing.

TR 2.13.1
B Reference Document disclaimer does not nullify DSC clause — GP 1-04.7 creates a carve-out Strong

Skanska Assertion (Penhall Feb 23 letter; LTR 359)

GP 1-02.2 contains an exception clause and GP 1-04.7 entitlement supersedes the Reference Document disclaimer. Deck thickness is a latent physical condition not reasonably discoverable. The disclaimer cannot eliminate DSC rights.

WSDOT Position

GP 1-02.2 disclaims reliance “unless stated otherwise in the Contract.” TR 2.13.1 IS a statement in the Contract — it explicitly disclaims dimensional accuracy of as-built drawings and places field verification on the DB. This provision both fulfills and limits the GP 1-02.2 exception: the contract does not guarantee dimensional accuracy; it requires the DB to verify. Additionally, GP 1-02.4(1) uses “conclusive evidence” language: the DB’s certification that it inspected the site and familiarized itself with surface and subsurface conditions is conclusive evidence of that fact.

GP 1-02.2 · TR 2.13.1 · GP 1-02.4(1)
C Type (b) DSC — overlay on 1967 bridge is unusual and unforeseeable Strong

Skanska Assertion (LTR 377)

The deck thickness variation constitutes a Type (b) DSC: “physical conditions of an unusual nature, differing materially from those ordinarily encountered.” A 1996 concrete overlay of varying thickness (1” at south to 2.5–3” at north) was not disclosed in as-built drawings and is unusual for bridge rehabilitation.

WSDOT Position

Bridge overlays are common maintenance on aging structures. A 1996 seismic retrofit overlay on a 1967 bridge is entirely foreseeable — not “unusual.” The 1996 overlay is documented in Appendix N02_5 (pg 83/95). Skanska had constructive knowledge. GP 1-04.7(a) requires the Design-Builder to have “no actual or constructive knowledge of such conditions as of the Proposal Due Date.” The overlay is in the as-built record — Skanska had constructive knowledge. Furthermore, Penhall’s baseline calculation uses 7.0” (ignoring the 1.5” overlay), inflating the apparent discrepancy; with the corrected 8.0–8.5” baseline, the south end shows effectively no discrepancy.

GP 1-04.7(a) · GP 1-04.7(b) · Appendix N02_5 pg 83/95
D Pre-bid coring of active I-405 bridge was not reasonably feasible Moderate

Skanska Assertion (LTR 377)

TR 2.13.1’s field verification obligation is a “design and construction performance obligation,” not a pre-bid investigation requirement. Verification of deck thickness required “destructive testing on an active interstate structure” — not reasonably feasible during procurement. Form A (ITP 3.3.4) “addresses general site familiarity and conditions discernible from the surface”; deck thickness is latent, not surface-discernible.

WSDOT Position

ITP Section 2.6 permitted proposers reasonable ROW access for data collection during procurement. ITP Section 2.7.3 placed investigation costs on the proposer. ITP Section 2.2 allocated risk of failure to investigate to the proposer. Skanska never requested ROW access for this purpose — the question was never asked. Crucially, deck thickness is also measurable from below the bridge structure via access hatches (without destructive surface testing), and non-destructive testing methods exist (impact-echo per ASTM C1383). The fundamental failure is not choosing the wrong method — it is never considering investigation at all. ITP 3.3.4 certification that Skanska “inspected and examined the Site” was a pass/fail requirement covering “surface and subsurface conditions.”

ITP 2.6 · ITP 2.7.3 · ITP 2.2 · ITP 3.3.4 · TR 2.13.1 · GP 1-02.4(1)
E Penhall baseline flaw — inflated 7.0” baseline ignores documented 1996 overlay Strong

Skanska Assertion (LTR 377 — Penhall mapping)

Penhall’s Deck Thickness Mapping uses 7.0” as the as-built baseline for all spans, showing discrepancies of 0.5”–4.0” and computing 192 CY of extra volume.

WSDOT Position

Penhall’s 7.0” baseline is incorrect. Appendix N02_5 (pg 83/95) documents a 1996 seismic retrofit overlay of ~1.5” nominal. The correct as-built total is ~8.0–8.5”. With the corrected baseline, discrepancies are: south end (spans 1–4) ≈ 0” (matches); middle spans 0.5”–1.5”; north end (spans 13–15) 0.5”–2.5”. Many spans in Penhall’s mapping that appear below the 7.0” baseline actually meet or exceed the corrected 8.0–8.5” baseline. The 192 CY extra volume calculation and $235K removal increase claim are overstated based on the wrong baseline.

Appendix N02_5 pg 83/95 · WSDOT field measurements (Feb 10, 2026)

3. Risk

Strengths

  • TR 2.13.1 is unambiguous and specific to bridge as-builts: disclaimer of dimensional accuracy + field verification obligation. No comparable provision in Vault NW12 (SL9727-079), making this case stronger than the precedent.
  • GP 1-01.3 and GP 1-02.2: as-built drawings (Appendix N2) are Reference Documents relied on “at its own risk.”
  • Modjeski and Masters memo (February 9, 2026) — Skanska’s own structural engineer concluded “no modification to demolition plans is needed.” The primary cost driver ($235K “5% removal increase”) is not supported by any methodology change.
  • Penhall baseline flaw: using 7.0” instead of 8.0–8.5” inflates the apparent discrepancy and overstates cost/volume claims.
  • ITP provisions prove investigation mechanism existed and cost/risk were allocated to proposers (ITP 2.6, 2.7.3, 2.2, 3.3.4).
  • Below DSC threshold: $378,613 ROM is far below the GP 1-04.7 $1.5M threshold even if entitlement existed.

Potential Weaknesses

  • Most vulnerable: a sympathetic DRB applying equitable reasoning about what a “reasonable” proposer would actually do — coreing an active I-405 bridge during procurement raises practical fairness concerns even if contractually required.
  • TR 2.13.1 “as required for their Work” timing ambiguity: Skanska argues this is a performance obligation (during construction), not a pre-bid obligation. The contract text does not specify timing.
  • No clear delineation of overlay layer in physical core samples (Hayden Wolf observation) — could complicate baseline argument if Skanska argues the overlay is not visually identifiable.

Defense Layering

LayerDefenseUse In
Primary TR 2.13.1 — explicit disclaimer of dimensional accuracy + Design-Builder field verification obligation Protest Response — Lead
Secondary GP 1-01.3 + GP 1-02.2 — Reference Documents relied on “at own risk”; no entitlement to rely Protest Response
Tertiary ITP 3.3.4 + GP 1-02.4(1) — “conclusive evidence” of site inspection; ITP 2.6 access mechanism existed; Skanska never requested access Protest Response (ITP 3.3.4 already in SL-264)
Forensic Penhall baseline flaw (7.0” vs. 8.0–8.5” corrected) — deflates discrepancy at south end to zero; M&M memo shows no methodology change needed Protest Response — Cost/Schedule Rebuttal
Reserve ITP 2.7.3 (“sole expense”) + ITP 2.2 (“bears the risk”) — investigation cost and risk allocated to proposers; GP 1-02.4(1) conclusive evidence for DRB; Vault NW12 precedent (SL9727-079) DRB Position Paper / Hearing

Fallback Position

The $378,613 ROM falls entirely below the $1.5M DSC threshold in GP 1-04.7. Even if entitlement were established, WSDOT’s first-dollar responsibility would be $0 — Skanska bears the first $1.5M. Engineering re-evaluation ($38,500) produced no actionable changes. The only material cost exposure is the north-end demolition adjustment (~$235K) which is unsupported by any methodology change (per M&M memo).

4. Chronology

WSDOT
Skanska
Milestone
Jan 2026 – Mar 2026 Full timeline →
Date Event
1967-01-01 Original bridge construction — deck: 6.5”–7” top slab (Appendix N02_5)
1996-01-01 Seismic retrofit — ~1.5” special concrete overlay added (Appendix N02_5, pg 83/95). Only 12 of 452 retrofit sheets in as-builts.
2022-10-25 RFP issued — Appendix N2 (Bridge As Builts) designated “R” (Reference Document) in Appendix A1
2025-02-21 WSDOT SL9727-079 — Denies Vault NW12 claim; cites Reference Document provisions. Establishes precedent for as-built disclaimer.
2026-01-24 TCP 119 demolition closure begins — full freeway closure for deck removal. Penhall discovers deck thickness variation during active removal operations.
2026-01-27 Penhall notifies Skanska (3 days after discovery) — claims deck exceeds as-builts by “approximately 2 to 4 inches”
2026-01-29 Skanska LTR 334 — DSC 007 notice (Skanska numbering). Attaches Penhall letter; annotated drawings show 9”–9.5” cores.
2026-02-09 Modjeski and Masters structural verification memo — concludes no modification to demolition plans needed despite increased dead load. Engineering cost: $38,500.
2026-02-10 WSDOT field coring — Hayden Wolf / Penhall coring observed by WSDOT. Results: ~8.5” south end (matches as-builts); 10–10.5” north end. Confirms measurement methodology (core length ≠ full deck thickness — tape measurement to 8.5” at span 4/5).
2026-02-12 WSDOT SL 9727-264 — Written Determination: DSC does not exist. Three grounds: (1) TR 2.13.1, (2) Reference Documents, (3) Form A certification.
2026-02-23 Penhall letter to Skanska — Rebuts all 3 WSDOT grounds; claims material deviation, latent condition, not reasonably discoverable
2026-02-26 Skanska LTR 359 — Notice of Protest 016 (SKA-0308). Requests 14-day extension. Attaches Penhall Feb 23 response.
2026-02-27 WSDOT SL 9727-283 — Protest acknowledgment. Denies 14-day extension. Supplemental deadline: March 13, 2026.
2026-03-12 Penhall supplemental letter — Cost/schedule impact summary: 4.5 weeks (4 wks engineering + 0.5 wks demolition); $298,500. Includes Deck Thickness Mapping (7.0” baseline — flawed).
2026-03-13 Skanska LTR 377 — Supplemental Protest (55-page package). Type (b) DSC; $378,613 ROM; 34-day schedule claim; 4 attachments. Filed on deadline day. No TIA submitted.

5. Cost & Time

Skanska’s Claim (LTR 377 — ROM)

CategoryAmountNotes
Engineering re-evaluation (M&M)$38,500$22K third-party + $16.5K re-eval. M&M concluded no changes needed.
Removal increase (5% premium)$235,000Scrutiny required: M&M says no methodology change needed
Extended overhead$25,000Not justified without methodology change
Other costs (markup, etc.)~$80,113Derived from total ROM
Total Cost Claimed (ROM)$378,613Below $1.5M DSC threshold
Schedule Extension34 calendar days (no TIA; PCO 010B controls critical path; Skanska reserves right to submit TIA later)

WSDOT Exposure Scenarios

ScenarioCostTime
WSDOT position (full denial)$0None
DRB partial (engineering costs only)~$38,500Nominal
Worst case (full award)$378,613TBD (if TIA submitted)
Note: Even if entitlement established, GP 1-04.7 $1.5M threshold means WSDOT owes $0 until aggregate DSC costs exceed $1,500,000. This claim alone triggers no payment obligation.

Coring Data Summary

LocationSpansMeasuredCorrected BaselineTrue Discrepancy
South end1–4~8.5”8.0–8.5”~0” (matches)
Middle5–129–10”8.0–8.5”+0.5” to +1.5”
North end13–1510–10.5”8.0–8.5”+1.5” to +2.5”
Penhall’s claimed 2–4 inch discrepancy uses 7.0” baseline (ignores 1996 overlay). Corrected discrepancy ranges from 0” (south) to 2.5” (north).