INTERNAL MEMO — DO NOT SEND
Contract No.: 009727
Project: I-405/Brickyard to SR 527 Improvement Project
Date: January 21, 2026 (updated February 2026 with LTR 344 protest response analysis)
Prepared by: WSDOT Contract Analysis Team
Subject: Analysis Supporting Denial of Skanska LTR 312 Force Account Claim ($196,848.74)
Responding to: LTR 344 (Feb 6, 2026) and LTR 357 (Feb 20, 2026)
This memorandum documents the analysis leading to WSDOT’s determination that Skanska’s $196,848.74 Force Account claim for contaminated soil removal at Site ID 6 (BNSF ROW) should be denied in full.
Primary Finding: Section 2.8.5.8 places known contamination handling within “The Work” for the lump sum Contract Price. Technical Requirements take precedence over GSP Mandatory Standards regardless of CO 040 per Section 2.8.2 and GP 1-03.2(2)’s “notwithstanding” clause. The Force Account payment provision (GSP 2-02.5.OPT7.GR2) is additionally excluded from integration by GP 1-03.3 and defeats itself by referencing GP 1-09.6, which excludes original scope items.
| Item | Value |
|---|---|
| Contamination Type | Arsenic (23.6 mg/kg > MTCA 20 mg/kg), Lead, TPH, Creosote, Lube Oil |
| Soil Classification | Class 2 / Class 3 |
| Site | King County Parks / Former BNSF Rail Line — Parcel 0926059170 (Site ID 6 in HazMat Report) |
| Volume Removed | 910.9 tons (28 loads; Nov 4–11, 2025) |
| Disposal Rate | $113/ton (Grady subcontractor) |
| Total Claim | $196,848.74 (LTR 312) |
| Contract Basis Claimed | GSP 2-02.5.OPT7.GR2 (Force Account); incorporated via CO 040 (per Skanska) |
“Known contamination has been identified within the ROW. The Design-Builder shall refer to the Hazardous Materials Report in Appendix E. All identified contamination shall be addressed in the RFC Documents… The Work shall include inspection, mitigation, handling, and disposal of any known or suspected contamination.”
This provision is dispositive. Known contamination handling and disposal are part of “The Work.” Per GP 1-04.1(1), the Contract Price includes all Work. No separate payment is available.
The contract establishes two distinct tracks — a deliberate design confirmed by the structural relationship between adjacent provisions:
| Track | Provision | Payment |
|---|---|---|
| Track 1 — Disclosed Contamination | Section 2.8.5.8 (identified in HazMat Report) | Lump sum Contract Price per GP 1-04.1(1). No DSC pathway. No separate payment. |
| Track 2 — Undisclosed Contamination | Sections 2.8.5.8.1 (Asbestos) and 2.8.5.8.2 (USTs) — “not identified within the Hazardous Material Report” | “May be considered a Differing Site Condition.” Routes to DSC/Change/Force Account. |
Site ID 6 contamination was disclosed in E09a2 and E09a5. It is Track 1. The lump sum Contract Price is the payment mechanism.
Section 2.8.2 (Mandatory Standards) explicitly lists “Special Provisions (Appendix B)” as Mandatory Standard #1 within the Technical Requirements. This is the link: GSPs are Mandatory Standards listed within the TR.
GP 1-03.2(2) provides:
“Notwithstanding the order of precedence listed above:… In the event of a conflict among any Mandatory Standards, the order of precedence designated in the Technical Requirements regarding said standards shall prevail. The Technical Requirements shall take precedence over all Mandatory Standards listed within the Technical Requirements.”
Chain is airtight: Section 2.8.2 establishes GSPs as Mandatory Standards within TR → GP 1-03.2(2) “notwithstanding” clause says TR controls over all such Mandatory Standards → Section 2.8.5.8 (TR) controls over GSP 2-02.5 — regardless of CO 040’s precedence position.
GP 1-03.3 incorporates Standard Specifications Divisions 2–9 “excluding measurement and payment Sections.” GSP 2-02.5.OPT7.GR2 is titled “Payment.” It is excluded from integration through the Standard Specifications pathway.
Even if the GSP were fully operative at Change Order precedence, it defeats itself: GSP 2-02.5 routes to “force account as provided in Section 1-09.6.” GP 1-09.6 excludes “an item which was included in the original scope of the Work.” Section 2.8.5.8 places this work in the original scope. The GSP’s own payment pathway leads to a dead end for Track 1 work.
Note on CO 040:
CO 040 was a no-cost version correction (Appendix B03: 2023 Std Specs → 2022). The Change Record states it “replaces Appendix B03 with the version that should have been issued at the time of the RFP advertisement.” GSP 2-02.5.OPT7.GR2 (dated December 4, 2006) predates both versions and was not modified. CO 040 did not create new payment entitlements.
E09a5 downgraded Site ID 6 from Moderate to Low risk specifically because “Construction activities are now limited to potentially using the area for staging.” The sampling requirement was conditional: “if the contractor proposes construction activities that would require any excavation.”
WSDOT did not require excavation at this location. Skanska, as Design-Builder, elected to excavate approximately 910 tons from a disclosed contamination site. This design choice triggered the contamination encounter. Skanska assumed the risk of consequences of their own design decisions. (Reserve this argument for DRB — do not lead with it in the determination letter.)
| LTR 312 Item | Amount | Disposition | Basis |
|---|---|---|---|
| SKA Labor | $17,771.14 | Deny | Lump sum per Section 2.8.5.8 |
| SKA Equipment | $6,337.03 | Deny | Lump sum per Section 2.8.5.8 |
| SKA Materials/Services | $23,216.68 | Deny | Lump sum per Section 2.8.5.8 |
| SKA Markup | $11,715.33 | Deny | No basis for markup on denied costs |
| Subcontractor (Grady) | $124,547.36 | Deny | Lump sum per Section 2.8.5.8 |
| SKA Sub Markup | $13,261.20 | Deny | No basis for markup on denied costs |
| TOTAL | $196,848.74 | Full Denial |
If full denial is deemed too aggressive after legal review, a partial denial position is available based on the GSP’s internal distinction between excavation (bid scope) and disposal (Force Account):
| Treatment | Amount | Rationale |
|---|---|---|
| Approve (disposal + markup) | ~$138K | GSP distinction: excavation is bid scope; disposal could be Force Account |
| Deny (excavation + markup) | ~$59K | Excavation was base scope per Section 2.8.5.8 |
Note: This position concedes that the GSP applies, which undermines the primary analysis. Do not offer this position in the determination letter. Reserve for post-DRB settlement consideration only if legally advised to do so.