| 2022-10-25 |
WSDOT |
RFP |
RFP issued. TR 2.18.4.6.3 requires bucket truck access for CCTV. Appendix M1 (Reference Document) shows existing camera on existing pole near NE 160th St. |
| 2023-07-01 |
— |
Contract |
Contract No. 009727 executed. All TR Chapter 2 requirements binding. |
| ~2024–2025 |
Joint |
(informal) |
Early design coordination. DB proposes CLD approach due to NE 160th overcrossing proximity. WSDOT and DB discuss CLD in Task Force meetings. Field walk conducted. AECOM characterizes outcome as “agreed solution.” |
| 2025-03-13 |
WSDOT |
RCSR |
WSDOT Maintenance rejects CLD at RFC close-out. Requires bucket truck access per TR 2.18.4.6.3. Related RCSR area grayed out. 8-month design standstill begins. |
| 2025-03-13 to 2025-11-05 |
— |
— |
8-month design standstill. Parties explore alternatives. Multiple meetings. Analysis of new alternatives discussed. |
| 2025-11-05 |
Joint |
Task Force Meeting |
Parties agree on solution: expand Comm Hub site for bucket truck access; CCTV pole must be relocated. |
| 2025-11-17 |
AECOM |
PCN-00100 |
AECOM issues Contract Change Scope of Work for CCTV Pole Pullout redesign. 5 disciplines. Attached to LTR 294. |
| 2025-12-09 |
Skanska |
LTR 294 |
Formal change order request. Claims bucket truck solution is “agreed-to solution with WSDOT.” Attaches AECOM PCN-00100. |
| 2025-12-24 |
WSDOT |
SL 9727-225 |
Written Determination denying change order. Cites TR 2.18.4.6.3, Appendix T1 §1.12.2.1, §2.3.2.3. “Work is included in Contract as written.” |
| 2026-01-07 |
Skanska |
LTR 313 |
Notice of Protest 012. Requests 75-day extension for supplemental. Timely (14 days from SL 225). |
| 2026-01-08 |
WSDOT |
SL 9727-236 |
Acknowledges protest. Denies 75-day extension. Grants 1 additional day for MLK holiday. Supplemental deadline: January 23, 2026. |
| 2026-01-23 |
Skanska |
LTR 330 |
Supplemental. $104,878.85 claim (AECOM $91,199 + Skanska $13,680). 5 disciplines, 347 hrs + 15% markup. Schedule entitlement “TBD — actual delay analysis pending.” |
| 2026-02-06 |
WSDOT |
SL 9727-261 |
Protest denied. Bucket truck access road required per TR 2.18.4.6.3. CLD not acceptable under Appendix B07. |
| 2026-02-20 |
Skanska |
LTR 354 |
Dispute Notification per RFP Section 1-04.5(1). Claims CLD was collaboratively developed with WSDOT. Asserts bucket truck requirement is a change to the Contract. Timely (14 days from SL 261). |
| 2026-02-23 |
WSDOT |
SL 9727-278 |
Acknowledges dispute. Will wait for written Dispute Referral per Section 1-04.5(1).18. |