Notice
Protest
Determination
Dispute
Hearing

1. Executive Summary

Decision Requested

Prepare WSDOT’s DRB position paper upon receipt of Skanska’s Dispute Referral per Section 1-04.5(1).18; defend denial of OIC for SR 522 Transit Hub roadway lighting requirements.

  • Recommendation: Deny — mounting height requirement is established by Sound Transit Design Criteria Manual; no Change Order warranted
  • Cost Exposure: $332,468 (AECOM design costs); construction TBD; schedule risk to Milestone C
  • Risk Level: Moderate — dispute filed; awaiting Dispute Referral

Core Question

Does the Sound Transit Design Criteria Manual’s pole mounting height requirement for SR 522 Transit Hub roadway lighting constitute a WSDOT-directed change entitling Skanska to an Owner-Initiated Change, or is it a Contract requirement the Design-Builder must meet at its own cost?

Skanska requested an OIC for SR 522 Transit Hub roadway lighting requirements, asserting WSDOT’s interpretation of mounting height requirements was unreasonable (LTR 255, Oct 17, 2025). WSDOT denied the OIC, found the proposed fixture acceptable, but required that the mounting height comply with the Sound Transit (ST) Design Criteria Manual. WSDOT approved an increase to 24 feet (SL 9727-199, Nov 17, 2025).

Skanska filed Notice of Protest 009 (LTR 285, Dec 1, 2025), asserting WSDOT’s interpretation was unreasonable and requesting 60 days for supplement. WSDOT acknowledged the protest but denied the time extension, requiring supplement by December 15 (SL 9727-214, Dec 9, 2025). Skanska’s supplement quantified design costs at $332,468 (AECOM) with construction TBD and noted schedule risk to Milestone C (LTR 306, Dec 23, 2025).

WSDOT issued a Determination of no merit (SL 9727-234, Jan 7, 2026). Skanska filed a Dispute Notification per Section 1-04.5(1) (LTR 325, Jan 22, 2026), noting a Time Impact Analysis is required but scope is pending. WSDOT acknowledged the dispute and awaits the Dispute Referral per Section 1-04.5(1).18 (SL 9727-253, Jan 29, 2026). No Dispute Referral has been received as of March 2026.

PCO
ISS-256
Amount Claimed
$332,468+
Time Impact
TBD (Milestone C)
Status
Dispute

2. Skanska Assertions and WSDOT Position

A WSDOT Mounting Height Interpretation Is Unreasonable Strong

Skanska Assertion

WSDOT’s interpretation requiring the mounting height to comply with the Sound Transit Design Criteria Manual is unreasonable and constitutes a WSDOT-directed change to the Contract. Skanska argued that its proposed fixture was acceptable but WSDOT imposed an additional mounting height requirement not clearly required by the Contract, making the OIC appropriate (LTR 285).

WSDOT Position

The ST Design Criteria Manual mounting height requirement is a Contract requirement applicable to the SR 522 Transit Hub. WSDOT’s determination confirms the proposed fixture is acceptable but the mounting height must comply. WSDOT approved an increase to 24 feet, which is an accommodation within Contract requirements, not a new mandate. The Design-Builder is responsible for designing the lighting system in compliance with all applicable criteria, including the ST Design Criteria Manual (SL 9727-199).

ST Design Criteria Manual · GP 1-04.1(1)(a) · Section 1-04.4(5)
B $332,468 Design Cost and Construction TBD Moderate

Skanska Assertion

The OIC to comply with WSDOT’s mounting height requirement resulted in design costs of $332,468 (AECOM) with construction costs TBD. The change also puts Milestone C schedule at risk, with a TIA required but scope pending (LTR 306).

WSDOT Position

Because the mounting height requirement is a Contract obligation, not a WSDOT-directed change, no cost recovery is available. If the Design-Builder incurred costs redesigning a non-compliant lighting scheme to achieve compliance, those costs are the Design-Builder’s responsibility under GP 1-04.4(5)(a) (errors/omissions in Design Documents) or GP 1-04.4(5)(k) (failure to comply with Contract requirements). The Milestone C schedule risk must be evaluated through a proper TIA demonstrating critical path impact.

GP 1-04.4(5)(a) · GP 1-04.4(5)(k) · Section 1-08.8
C WSDOT Denies Time Extension for Supplement Available

Skanska Assertion

Skanska requested 60 days to prepare the protest supplement (LTR 285), arguing the complexity of the AECOM cost analysis warranted additional time.

WSDOT Position

WSDOT denied the time extension request, required supplement by December 15, 2025 (SL 9727-214). Skanska ultimately submitted the supplement on December 23, 2025 — eight days after the deadline. This late submission may affect the procedural record and is available as a defense argument if needed.

Section 1-04.5 · SL 9727-214

3. Risk

Strengths

  • The ST Design Criteria Manual is a Contract-referenced document; compliance is the Design-Builder’s obligation, not a WSDOT-directed change.
  • WSDOT approved the fixture type and a mounting height increase to 24 feet, demonstrating good faith accommodation within Contract requirements.
  • Skanska submitted the supplement late (Dec 23 vs. Dec 15 deadline), which may affect procedural posture.
  • No Dispute Referral has been received as of March 2026, limiting WSDOT’s obligation to respond further until referral is filed.

Potential Weaknesses

  • The $332,468 AECOM design cost quantum is relatively large; if the DRB finds partial merit, exposure is significant.
  • Construction costs remain TBD and could substantially increase total exposure.
  • Milestone C schedule risk requires a TIA; if critical path impact is demonstrated, time exposure could be meaningful.
  • Interpretation of whether the ST Design Criteria Manual’s mounting height requirement applies to the specific fixture context may be contested.

Defense Layering

LayerDefenseUse In
1.ST Design Criteria Manual mounting height is a Contract requirement; no OIC warranted under Section 1-04.4DRB Referral
2.GP 1-04.4(5)(a)/(k): cost of bringing non-compliant design into compliance is Design-Builder’s responsibilityDRB Referral / Hearing
3.WSDOT accommodated Skanska by approving 24ft height; this was not a new mandate but a compliant alternativeDRB Referral
4.Late supplement submission (Dec 23 vs. Dec 15 deadline) — procedural argument if neededReserve

Fallback Position

If DRB partially favors Skanska on the mounting height interpretation, WSDOT should limit any award to incremental design costs above what a compliant initial design would have cost, excluding rework costs attributable to Skanska’s initial non-compliant design. Construction costs and schedule impacts should be evaluated independently via TIA once submitted.

4. Chronology

WSDOT
Skanska
Milestone
Oct 2025 – Feb 2026 Full timeline →
Date Event
2025-10-17 Skanska LTR 255 — Requests OIC for SR 522 Transit Hub roadway lighting requirements
2025-11-17 WSDOT SL 9727-199 — Denies OIC; proposed fixture acceptable but mounting height must comply with ST Design Criteria Manual; approves increase to 24ft
2025-12-01 Skanska LTR 285Notice of Protest 009; asserts WSDOT interpretation unreasonable; requests 60 days for supplement
2025-12-09 WSDOT SL 9727-214 — Acknowledges protest; denies time extension; supplement due December 15
2025-12-23 Skanska LTR 306 — Supplement; design costs $332,468 (AECOM); construction TBD; schedule at risk for Milestone C (8 days after deadline)
2026-01-07 WSDOT SL 9727-234 — Determination of no merit
2026-01-22 Skanska LTR 325 — Dispute Notification per Section 1-04.5(1); TIA required but scope pending
2026-01-29 WSDOT SL 9727-253 — Acknowledges dispute; awaits Dispute Referral per Section 1-04.5(1).18

5. Cost & Time

Skanska’s Claim

CategoryAmount
AECOM design costs (Transit Hub lighting redesign)$332,468
Construction costsTBD
Total Cost Claimed$332,468 + TBD
Schedule ExtensionTBD — Milestone C at risk (TIA pending)

WSDOT Exposure Scenarios

ScenarioCostTime
WSDOT position (ST Design Criteria Manual is a Contract requirement)$0None
DRB partial (incremental design cost over compliant baseline)Partial of $332,468Limited
Worst case (full design + construction + schedule)$332,468 + construction TBDMilestone C delay TBD